    Exercise 1  Web site Development

    Using Microsoft Project  2007 (can be downloaded from internet)

    A nonprofit organization would like to lead a website development project. The organization has internet access that includes space on a web server, but no experience in developing websites. In addition to creating its website, the organization would like you to train two people on its staff to do simple web page updates. The website should include the following information, as a minimum: description of the organization (mission, history, and recent events), list of services, and contact information. the organization wants the website to include graphics( photographs and other images) and have an attractive, easy way to use layout.

     

    1- Project Scope Management: create a WBS for this project and enter the tasks in project 2007. Create milestones and summary tasks. Assume that some of the project management tasks are similar to tasks from the project tracking database project. some of the specific anaylsis, design, and implementation tasks will do:

    a) collect information on the organization in hardcopy and digital form( brochures, reports, organization charts)

    b) research web site of similar organization

    c) collect detailed information about customer's design preferences

    d) develop a template for the customer to review (background color of pages, layout of text)

    e) create a site map or hierarchy chart showing the flow of website

    2- Project Time Management:

    a) enter realistic duration for each task, and then link the tasks

    b) do Gantt Chart view and Network Diagram View  for the project

    c) do schedule table to see key dates and slack times for each task.

     

     

     

     

    3- Project Cost Management

    a) assume you have three people working on project and each of them would charge $20 per hour. Enter this information in the Resource Sheet.

    b) estimate that each person will spend an average of about five hours per week for the four month period. Assign resources to the tasks, and try to make the final cost in line with this estimate

    c) do a budget report for your project

    4- Project Human Resource Management

    a) assume that one project team member will be unavailable due to vacation for two weeks in the middle of the project. Make adjustments to accommodate this vacation so that the schedule does not slip and the costs do not change. Document the changes from the original plan and the new plan.

    b) use the Resource Usage view to see each person's work each month. Print a copy of the Resource Usage view.

    5- Project Communications Management

    a) do a Gantt chart for this project. use a time scale that enables that chart to fit on one page. and the copy and paste it to PowerPoint

    b) do a TO DO LIST report for each team member

    c) Create a WHO DOES WHAT REPORT

     

     

    ** Write a two page single spaced paper summarizing what do you think about Microsoft Project. What do you like and What do you dislike about it. Do you think it would be useful for managing all project or just some and which ones.

     

     

    posted on 2013-03-10 18:16 paulwong 閱讀(383) 評論(0)  編輯  收藏 所屬分類: Project Management

    主站蜘蛛池模板: 一区二区视频免费观看| 最近中文字幕大全中文字幕免费| 亚洲视频在线一区二区| 久久香蕉国产线看免费| 久久精品国产亚洲av麻豆蜜芽| 国产伦一区二区三区免费 | 337P日本欧洲亚洲大胆精品| 国产亚洲情侣一区二区无| 国产91免费视频| 九九全国免费视频| 久久精品国产亚洲αv忘忧草| 亚洲精品成人区在线观看| 色影音免费色资源| 国产区在线免费观看| ass亚洲**毛茸茸pics| 亚洲午夜福利AV一区二区无码| 免费可以在线看A∨网站| 中文字幕在线免费看线人| 亚洲欧美成人综合久久久| 亚洲成在人天堂一区二区| 国产成人在线免费观看| 最近免费中文字幕大全免费版视频| 免费国产va视频永久在线观看| 久久亚洲精品成人AV| 亚洲综合国产精品第一页| 好爽…又高潮了毛片免费看| 久久精品电影免费动漫| 一级A毛片免费观看久久精品 | 最近免费中文字幕mv电影| 亚洲第一视频在线观看免费| 亚洲精品无码专区在线播放| 久久精品国产亚洲77777| 狠狠亚洲狠狠欧洲2019| 四色在线精品免费观看| 永久在线免费观看| 成人无码WWW免费视频| 特级毛片在线大全免费播放| 亚洲精品美女久久久久久久| 亚洲一区二区三区久久| 亚洲欧洲日产国码www| 久久91亚洲精品中文字幕|